Location:
Naryan-Mar, Russia
Customer:
Ministry of Transport of the Russian Federation
Customer-Developer:
Federal State Unitary Enterprise “Naryan-Mar United Air Group”
Construction Project Period:
2003-2005
Project Description
The Naryan-Mar Airport reconstruction project provided for the reconditioning repair of the runway pavement, including:
- Removal of PAG slabs
- Grade leveling after slabs removal
- Construction of stabilized base
- Installation of new PAG slabs
- Filling of slab pavement joints with sand-and- cement mix and sealant.
- Repair of damaged slab spots
Provided Services
JSC Progresstech, Ltd. performed the following reconstruction works at Naryan-Mar Airport under the state contract awarded by the Russian Ministry of Transport as a result of the bid for general contractor selection:
- Construction management and supervision
- Execution of construction works
- Sealing of joints
- Quality control of the executed works
- Procurement of construction and repair materials
The compulsory certification is to be performed by the airport certification agency and appropriate regional certification bodies duly accredited by the Russian Federation air transport certification system. Widely used for certification are relevant certification centers and testing laboratories.
The increase of the performance period of airfield and roadway pavements depends on such factors as proper operation, adequate maintenance and timely running repair to be performed in accordance with the relevant norms and standards. The construction & repair units of JSC Progresstech, Ltd. and Progresstech-Center perform all kinds of works for airfield and roadway pavement repair using advanced technologies and knowhows, state-of-the-art equipment and materials.